Al-Ghous Street project 42.5% completed

This news has been read 8593 times!

KUWAIT CITY, May 19: Project Engineer of construction, completion and maintenance of Al-Ghous Street project phase 1 Eng Khalid Al-Me’raj disclosed that 42.5 percent of the project has been completed when 32.8 percent was supposed to be completed by May 2018, affirming that the project execution is on schedule.

He highlighted the benefits of the project in refurbishment and development of the road network in the country, stressing that the Al-Ghous project is one of the important projects being executed by the Public Authority for Roads and Transport that will contribute to offering infrastructure and good services based on international standards